STATUS/ACCOMPLISHMENTS This week we conducted detailed schedule reviews with approx. half of our subsystems and we will continue next week. In addition to tracking, we focused on detailing & integrating a 6 month rolling wave schedule with each subsystem. We also started discussions with the GSFC Resource Analysis Office (RAO) regarding their independent cost estimate. RAO has a draft of the S/C portion which needs a little more work but is close to our grassroots estimate. Next week we will have discussions with RAO in the instrument & ground system areas. The systems team also participated in the subsystem schedule walkthroughs, using the opportunity to provide input in the subsystem development flow, deliverable linkage for the subsystems, & address other technical issues related to the subsystem development. The mechanical & propulsion teams completed a draft of the updated mechanical and propulsion subsystem concept which is being reviewed by the rest of the SDO team. This update addresses mass, volume, & robustness areas identified by the Project & SCR review teams. As part of the development process, the systems team participated in a variety of technical and development issues, such as instrument accommodation issues, ground system requirements, science data capture and completeness budget updates, single board computer requirements and procurement issues, electrical specification development, and spacecraft timing concept review. In the area of power, we are revisiting our solar array sizing & electronics approach to ensure proper design/margin. To meet the worst case (failed battery cell) exit of eclipse voltage conditions at end-of-life, we are assessing possible options which include: increasing available power from the array, modifying the electronics operation to include some form of buck regulation, or some combination of both. For the Instruments, work continued on the accommodation of the reorientation of the SPECTRE assembly of the SHARPP instrument. The preferred solution is converging and we are working the details. Relocating the KCOR CCD camera electronics and providing unobstructed CCD and instrument radiator fields of view for all of the SHARPP assemblies are the challenging constraints. We have a face-to-face meeting with the NRL SHARPP team this Friday (5/9). Work also continued on the consolidation of the baseline instrument interface requirements and the draft content of the associated instrument ICDs. We have generated ICD outlines for the subsystems we have previously interviewed. A great deal of the credit goes to Steve Merrihew who is spearheading this effort. We also worked closely with the SDO Program Exec to update a critical international Letter of Agreement (LOA) with Italy for their contribution of the SPECTRE assembly to the SHARPP instrument suite. We incorporated and reconciled extensive LOA comments from the HQs international group. The substance of the agreement remained fundamentally unchanged however there was significant language change proposed which was addressed. The CCD and camera electronics modification (eng. units/demo) to the NRL contract is in place which enables NRL to start the joint buy for the HMI and SHARPP teams. The HMI and SHARPP teams will visit E2V (CCDs) and RAL (camera electronics) next week to kick off the effort. EVE continued their series of internal subsystem peer reviews to consolidate and integrate EVE system requirements. Peer reviews for the MEGS electrical interface, low voltage power supply, and thermal subsystems were completed. Mechanical subsystem and flight software peer reviews are scheduled for next week. The results of these internal review will be consolidated into a presentation to the EVE science team on May 22-23. This baseline will be the basis for EVE's plans and costs estimates which will be provided in the Phase A Concept Study Report (CSR). In fact, EVE has completed their first cut at the draft CSR and it is being circulated internally for comment. HMI completed their reliability enhancement study and provided detailed charts to the project. The SDO systems group is reviewing the data and will make a recommendation so that a decision on the enhancements can occur within 2 weeks. ICD definition work continues with specific discussions in the areas of: thermal models, mechanical model and accommodations, 1553 bus communications, ground system Science Operations Center interface, electronics box configuration, and launch loads. The HMI preliminary parts list has been reviewed by the SDO parts engineer and comments have been provided to the HMI team. For Flight Assurance, the Reliability group continues to define the schedule objectives of the reliability effort between SCR and PDR (12/03). Specific work assignments have been distributed and the group is meeting weekly to share results. Biweekly status meetings are held to status the progress of those objectives. General objectives include the Reliability Block Diagrams, Fault Tree Analysis, Probabilistic Risk Assessment, & the Failure Modes & Effects Analyses. System specific areas include the Ka-Band subsystem, HMI reliability assessment, High gain antenna deployment approach, propulsion system, battery configuration assessment, and ground system reliability/availability. In the area of Risk Management (RM), the SDO RM coordinator began the monthly update of SDO risks in preparation for our end of month Risk Management Review Board meeting. We also began working with the GSFC Systems Management Office to create an SDO-specific Risk Management Training curriculum. In the area on CM & Project Support, the team continues to coordinate comments to the Mission Assurance Requirements document & is in the process of updating the action item database with the systems team. In addition, the CM team conducted an outstanding demo of our soon (mid June 2003) to be on-line Document & CCR system. The Project Support group continues working Property activities, key cards, Travel Manager training, office facility updates, Project documentation, & financial training. Thanks, Ken "Failure can be bought on easy terms; success must be paid for in advance." Cullen Hightower [ Attachment (text/x-html): 6603 bytes Character set: iso-8859-1 Encoded with "quoted-printable" ]