STATUS/ACCOMPLISHMENTS We completed our detailed schedules review and our subsystem leads are preparing for our first internal monthly status review (cost/schedule/technical status). We also provided additional information to GSFC RAO and the IRT for their cost modeling. This included RAO worksheets for the European instrument contributions to SHARPP and TRL (Technology Readiness Level) worksheets for all instruments along with a detailed breakdown of our avionics to the IRT. Independent Review Team update: They are close to having a draft assessment & have identified a few areas which we will work with them to provide additional information/clarification. They are still probably about 1-2 weeks away from having their independent cost estimate complete. Their work along with our preparations/support may take the majority of June which makes scheduling of the management meetings difficult due to vacations. We are currently trying to setup all the meetings so that the ICR with the Enterprise PMC occurs the end of July. Code S informed us that our ICR will be at the EPMC and not at the Agency Level. However, the CR will be at the Agency Level. The systems engineering team has been working with the electrical systems team in a comprehensive review of the electrical systems specification in preparation for review by the SDO team. In addition, the weekly SDO systems team meeting focused on walking through the current status and various options associated with the solar array sizing trade. As part of the monthly Risk Management cycle, the systems team met with the SDO risk coordinator to walk through and assess the status of the current risk items in preparation for next week's Risk management board, as well as generating and evaluating new additions to the SDO risk list. Finally, further definition of the requirements generation and documentation approach was ongoing, with the goal of providing a more comprehensive plan and guidance to the subsystems teams in their ongoing requirements generation and documentation process. In addition, systems & the GSFC instrument team started the discussions on the use and requirements for the baselined Spacecraft simulators which will be provided to the instrumenters. For the instruments, the team completed interface coordination discussion with the ACS subsystem group to identify ACS to instrument interface requirements and candidate ICD content. Direct ACS interfacing with the instruments is limited, however there is a direct interface with the NRL provided Guide Telescopes which needs to be well defined and documented. We are working with the instrumenters to determine appropriate areas for initiating early procurement activities for schedule critical and long lead items such as mechanism life tests, CCDs, & optics. All of these are documented, coordinated with HQ, & within this budget/phasing. NRL & HMI visited e2v & RAL last week in the UK to discuss CCD and camera development respectively. The e2v CCD mask design is in process with completion and approval set for the second week of July. NRL, HMI, and GSFC representatives will attend the PDR at e2v at that time. RAL camera progress is continuing & we are evaluating the possibility of HMI furnishing the electronic parts to RAL to facilitate camera builds. The Project agreed to the HMI reliability enhancements resulting from a study completed by HMI & GSFC. The enhancements add redundant mechanisms and electronics including a second processor to boost the probability of full and minimum mission successes. Both HMI & NRL provided a draft outline of the concept study report due at the end of June for comment. The SDO Mission Assurance Requirements (MAR) document went through its initial configuration control board (CCB) meeting with near flying colors. A limited number of action items were identified. The plan is for these items to be completed and modifications incorporated into the MAR by next week so that the document can be baselined and placed under configuration management (CM) control by week's end. Wentworth Denoon, the Director of Code 300, Office of System Safety and Mission Assurance and I will jointly approve the baselined MAR document. CM & Project Support accomplishments: 1) the team did an excellent job preparing for our first CCB with the MAR; 2) continued working action items with systems; 3) gathered data from subsystem leads to update the SDO housing requirements that were submitted to the LWS Program Office in January; 4) started working with modular/systems furniture representative to develop a plan for temporary walled offices in Bldg. 29/Room 360; 5) updated the Solar Dynamics Observatory (SDO) Project Team Phone List and E-mail distribution lists. Thanks, Ken "The greatest problem in communication is the illusion that it has been accomplished." George Bernard Shaw British Author & Socialist [ Attachment (text/x-html): 5203 bytes Character set: iso-8859-1 Encoded with "quoted-printable" ]