STATUS/ACCOMPLISHMENTS This week the systems/subsystems team focused on the Observatory mechanical bus design, with the mechanical team providing an update of their detailed design work since the SDO SRR/SCR. The update addressed many of the design and implementation issues raised both at the review itself and afterwards. As part of the ongoing subsystem definition and design process, subsystem teams provided the systems team with an initial draft cut of their Level 3 requirements. In addition, the process of updating the Mission Requirements Document (MRD), which contains many of the driving SDO Level 2 requirements, has begun, beginning with previously provided instrument updates. Systems/subsystems work also continued in a variety of development areas, such as cPCI implementation, SDN design approach issues, and Electrical System Spec development. Weekly High Gain Antenna meetings continued and a number of splinter groups were established for pointing, calibration, Mechanical/RF, ACS interface, gimbal, electronics, dynamic analysis, and test flow. Finally, the GN&C team presented an excellent trade study update on the propulsion system options as part of their ongoing process to address issues raised at the SDO SRR/SCR and to move ahead in the preliminary design process. Progress continues to be made on the Single Board Computer (SBC) procurement. The SBC Statement of Work and Specification are nearly complete and a meeting to work some areas with SDO Contracts was conducted this week. For the Instruments, the Instruments teams are busy completing their Phase A Concept Study Reports which will start to be delivered next week. Progress also continues in the area of spacecraft simulators with the requirement/functions discussed in the weekly Instruments' telecon. CCD specifications and packaging were updated by e2v and discussed in the weekly CCD/Camera electronics telecon. Plans are going ahead for the peer review of the CCD at e2v on July 16th and camera electronics at RAL on July 17th. The ground system team received 8 ASIST workstations (command & telemetry GSE) this week. GSFC Building 23, room C110 will host the initial setup and integration of these workstations which will be offered as a mission development lab for future use. This facility has raised flooring with sufficient power, network connections, & work and desk space. Progress continues on the Ops Concept Document, Detailed Mission Requirements Document (DMR), and ground system schedule. A SOC to MOC commanding interface document is also being drafted. Now that the SDO Mission Assurance Requirements (MAR) document has been baselined, the flight assurance team is concentrating on base-lining the suite of supporting plans that identify how SDO will satisfy the MAR. The Configuration Control Board (CCB) meeting for the System Safety Program Plan (SSPP) is scheduled for July 10th. The Reliability Program Plan (RPP) and Risk Management Plan will be scheduled for later in the month. In the area of reliability, the team developed a Reliability Block Diagram (RBD) and a Fault Tree (FT) for the deployable systems and will meet with the deployable systems lead next week to go over the RBD & FT along with design options. The HMI (Lockheed Martin) draft Software Management Plan has been received and is being reviewed for compliance to the applicable portions of the SDO Mission Assurance Requirements (MAR) document. The parts team resolved board layout issues with the Subsystem Data Node (SDN) prototype design and completed the parts kit & delivery of components needed to build the 2 SDO SDN prototype boards. Our Parts lead also traveled to International Rectifiers (IR) Advanced Analog division in Santa Clara, California to gather additional information on their M3G converters which may be used on the SDO program (S/C & possibly HMI & EVE). In the area of CM & project support, the team: continues to work the SBC CCR process; updated the action item database with responses received this week; provided comments to ISO documents; continues to evaluate the intranet database screens & address issues in preparation of making the system available next week; started coordinating the CCR for the modification of the HMI SOW for reliability enhancements; reached a verbal agreement with both ASTRO-E2 for SDO to begin occupying a major portion of their cubicle space in Bldg. 29/Rm. 360 in late fall /early winter of 2003 and ST-5's space in late 2004. Bob Vernier, the Bldg. 29 Building Manager, has concurred with this plan. SDO personnel also participated in Celebrate Goddard Day by manning a booth for the Goddard Fitness Club. Thanks, Ken "One of the illusions of life is that the present hour is not the critical decisive hour. Write on your heart that every day is the best day of the year." Ralph Waldo Emerson American Poet & Philosopher [ Attachment (text/x-html): ".prt44830fcbbb" 5195 bytes Character set: iso-8859-1 Encoded with "quoted-printable" ]