STATUS/ACCOMPLISHMENTS The weekly systems team meeting addressed the SDO power budget study, dealing specifically with the solar array and battery sizing to address SDO operational and EOL power reqs. This has been an ongoing investigation on meeting SDO EOL (end of life) requirements in light of potential hardware faults and mission requirements. The SDO power team reviewed the options investigated over the last few weeks and the assembled team defined the next stages required in identifying the final implementation approach to be taken. The HGA development team held an excellent review of the draft HGA development and qualification flow, further defining the issues at hand and helping to identify potential development approaches. The GN&C team held their subsystem peer review, where they provided a detailed walk through and traceability of their complete GN&C requirements, as well as their subsystem implementation and development approach. The Peer Review included independent GN&C discipline experts and RFAs were generated. The Electrical systems team completed their work on the draft Electrical Systems Spec and submitted it to the SDO spacecraft team for initial internal team review. The Radiation requirements specification, which further defines the SDO radiation environment throughout all phases of the SDO orbital mission, was also released to the SDO team after review and comment by the SDO systems team. The GN&C team met with the SDO systems team and project to discuss their latest trade information on the SDO reaction wheel make/buy trade study and what steps should be taken next in order to make a final selection decision. Finally, the systems team worked with the SPN and SDN development teams to help further define the implementation concepts and help define final design decisions and move the development process forward. Progress continues to be made on the SDN Prototype with phase one of four phases of populating and testing completed. Next week we will conduct our second internal project status review with each of our subsystems. Our next Champion meeting, which our LWS program & HQs customers are invited to attend, will be 7/24 at GSFC. The Instruments teams have started deliveries of their Phase A Concept Study Reports. Plans/approvals are in place for GSFC/NRL/HMI to participate in the e2v CCDs and RAL camera electronics peer reviews on July 16 & 17 in the UK. The ground system team focused on completing the draft versions of the Detailed Mission requirements document and the OPS Concept Document which will receive a wider distribution for review. The data distribution team received 18 responses to the mass storage RFI that closed on 6/26. They are reviewing these responses as well as clearing the IN-SNEC (French) company through Code 100 for a product demo on 7/28 related to the RFI. Also, the team completed their Command Security Risk Assessment for SDO which they will present to the project next week. In the area of CM, the team: has been working to fix "bugs" in the intranet database; preparing the CCR for the Reliability Enhancement of HMI; collecting informal comments for the System Safety Program Plan and the SDO Electrical Systems Specification before formal review/CCR processing; coordinating comments from latest review for the Single Board Computer SOW and Specification; and supporting preparations for next week's internal project status review. Thanks & have a Fun & Safe Holiday weekend, Ken Note: I will be on annual leave 7/3 - 7/11. During may absence, please contact my Deputy, Rob Lilly, for assistance. ############################################# second message ############################################# I forgot to mention that we have all Initial Confirmation Review meetings scheduled as follows: ICR Readiness (ICRR) with GSFC PMC: 8/5, 1:30-4:30, Bldg. 8/MCC. Summary briefing to GSFC Center Director: 8/7, 3:30-4:00, Bldg. 8/6th floor Conf. Rm. ICRR briefing to Code S Deputy AA: 8/25, 9:00-10:30, HQ/Rm. 3C35. ICR with Code S Enterprise PMC: 8/27, 9:00-11:30, HQ/Rm. 3C35. Thanks, Ken