STATUS/ACCOMPLISHMENTS I thank the entire SDO team for supporting the GSFC Initial Confirmation Readiness Review. The review went very well with commendations for our review chairs. After the ICRR, we met with GSFC's Resource Analysis Office to follow-up on actions from the review. The next step towards the 8/27 ICR starts next week with the reconciliation of the IRT's Independent Cost Estimate. The weekly systems team meeting covered the topic of Observatory grounding, with the focus on box-level grounding design guidelines. In addition, the High Gain Antenna (HGA) team held a very successful peer review of the HGA system concept, design, and development flow concept. Feedback from the peer review was very positive and provided excellent inputs in the further development of the HGA system and development approach. The Propulsion team held an excellent meeting with the Project to complete the discussion of the various propulsion design options. In addition, the Contamination team conducted a peer review which ensured that a Monomethyl Hydrazine (MMH) propulsion system meets SDO/Instrument contamination requirements. The result of AETD's great work is that the Project concurs with Code 597's recommendation to use a MMH system for SDO. The system includes a single 100 lbf main engine (MMH bi-prop) used to get to GEO orbit from GTO along with 8 MMH bi-prop 5 lbf thrusters used for ACS control & orbit raising redundancy. This configuration closely resembles commercial GEO spacecraft and provides dual fault tolerance in achieving our GEO orbit. The other good news is that this system is within or cost, schedule, & technical allocations. GREAT JOB PROPULSION TEAM! In the Instrument area, a few administrative items were worked this week including an interview with a Instrument Manager candidate and organizing/preparing CCRs for EVE contract modifications associated with the accelerated start of EVE's CCD efforts with MIT Lincoln Labs (Project controls/manages thru an Air Force tasking arrangement). Also spent some time gathering up reference SOWs from a variety of GSFC projects which will be culled for relevant SOW content for Phase BCDE contracts with the SDO instruments. On the technical front, a Project technical team visited the SHARPP instrument team at NRL to peer review the evolving SHARPP electronics design. NRL has simplified the electronics configuration for both cost and spacecraft accommodation reasons. Preparations continue for our next ICD session with the instrument teams. The redlines and comments extracted from the visit to the HMI team two weeks ago has been worked and incorporated in the latest versions of our ICDs. Detailed technical interface discussions are planned with the EVE team August 19 and 20. Similar discussions are planned with the SHARPP team in early to mid September. We also have an ICD follow-up meeting with the HMI team planned in early September. The Mission Assurance Team has been evaluating the mission assurance documentation supplied by NRL in support of the SHARPP instrument suite. Documentation reviews were completed on their draft Performance Assurance Implementation Plan (PAIP), and Contamination Control Plan. The draft PAIP's discrepancies against the SDO Mission Assurance Requirements (MAR) are being compiled and will be forwarded to NRL for discussion/action. Reliability models for three different design configurations of the Propulsion System were developed using fault trees to compare reliability of the three configurations. In the area of CM, the team is working on the final draft version of the CM Procedures and electronic CCR form (with instructions). In addition, the team is reviewing and will be providing comments on EVE CM plan. Thanks, Ken [ Attachment (text/x-html): 3989 bytes Character set: iso-8859-1 Encoded with "quoted-printable" ]