The systems team spent a significant part of the week supporting the HMI instrument team visit and participating in clarification discussions on a variety of Technical implementation and interface areas. In addition, the systems team assembled and released preliminary PDR guidelines to the SDO team to facilitate preparation for upcoming Subsystem PDRs. The team is also developing additional guidance to subsystems on PDR content and the peer review process that should be available for release shortly. The SDO document tree is being reviewed in light of the approach subsystem and mission PDRs with an eye of identifying and prioritizing key mission and subsystem documentation needed at these upcoming PDRs. In the area of SDO preliminary design work and hardware development, the SDN team delivered the SDN prototype to the SDO software lab this week to allow the S/W to begin SDN software development efforts - GREAT JOB SDN team! The Radiation team is in the process of assessing the results of the ATMEL 1355 part radiation testing in order to provide a use assessment to the SDO project. Members of the Power System Team and Mechanical System Team completed a detailed solar array cell packing factor analysis, which results in a revised estimate of 86% panel coverage with solar cells (versus 83% assumption baseline). The calculated SDO solar array power output capability will improve by almost 10% as a result of the analysis (from 135 solar array strings to 148 solar array strings) - this alleviates any potential solar array power output issues. Finally, the systems team met with the SDO AETD champion as a follow up to last week's AETD SDO/GPM architecture meeting in order to address issues raised during that time. The C&DH team held a number of board level pre-fabrication breadboard peer reviews this week. The business team has developed an earned value tracking approach and started to review with SDO PIs to obtain agreement. The HMI team visited GSFC this week to review ICD Rev. 2, current actions and program items. Mechanical, thermal, C&DH, GN&C, Operations and other items were discussed in detail. Both teams were well prepared and significant progress was made in readying the ICDs for baselining and configuration control in preparation for PDR. HMI has planned a series of instrument subsystem peer reviews over the next two months leading up to their Instrument PDR in November. The SDO team will participate in these reviews. Potential common parts buy items were discussed and a weekly working group meeting will be initiated next week. Candidate item lists are being generated by both the HMI team and SDO. A plan was formulated for contract continuity with the PIs consisting of extensions to the current contract and a new target date of January 15, 2004 for the phase B/C/D/E contract start. In the area of CCDs, e2v is in the midst of the thin-gate wafer run of the preferred demonstration CCD devices and things are proceeding normally. e2v will shortly start the production run of the backup thick gate demonstration devices. Initial probing of the first wafers is scheduled for end of October and these results should be ready for HMI/SHARPP PDRs. Radiometric characterization of these initial devices does not begin until the end of the year. The probe test is an inline process that electrically confirms the quality of masking and is a good indicator of basic device operability. The CCD working group discussions have concentrated on the CCD packaging, the RAL camera design progress, and the generation and review of development schedules from both teams. EVE efforts during the past week revolved around developing initial draft outlines for the upcoming PDR and the continued evolution of hardware and software designs. Fabrication of prototype parts for the CCD Mount and the Filter Mechanism has been completed, pre-fit checks are done, and the parts are being readied for shipment to a surface coating house. The Ground System team completed their package/preparations for their Systems Requirements Review (SRR) on 9/30/03. Operational Concept, Detailed Mission Requirement (DMR) and Project Management Plan (PMP) documents are in final draft form and will also be presented to SRR board members with the SRR package. In addition, the team presented the first draft of a commanding concept to the HMI team during their GSFC visit this week. Copies of this commanding concept have been forwarded to both SHARPP and EVE science teams as well. Finally, TSI Corporation is planning a product demonstration of their ground system Front End (data) Processor (FEP) the week of 22-26 September. This is the second demonstration of a Ka-band, commercially available FEP product. The CM team spent a good portion of the week working through intranet database issues. Today CM will announce to the SDO team that the system is available to access documents. Thanks, Ken "Its kind of fun to do the impossible" Walt Disney [ Attachment (text/x-html): 5281 bytes Character set: iso-8859-1 Encoded with "quoted-printable" ]