We received our Initial Confirmation Review (ICR) letter from Code S which confirms the SDO Project to transition from Phase A to Phase B. However, the SHARPP investigation did not pass the ICR. Therefore, SDO will proceed without the SHARPP investigation. The Project & NRL are in the process of working closeout activities. In order to preserve the SDO science, HQ has tasked us to issue a formulation contract to Lockheed Martin Advanced Technology Center for their AIA investigation. Lockheed was the other AIA bidder during the SDO Announcement of Opportunity process. The SDO Project wishes to express our appreciation for the efforts that NRL and their team members have made towards the SHARPP investigation. We wish them success in their future endeavors. We completed this month's round of Project Monthlys which were postponed due to the storm last week. The subsystem leads presented schedules based on the new launch date (4/08). We'll continue to fine tune and make sure all the schedules are linked properly over the next few weeks. We also began preparations for a late October kick-off meeting with KSC in order to understand/start the SDO Launch vehicle procurement process. As the subsystem PDR season approaches, the systems team has spent the last couple of weeks involved in several efforts to prepare for the upcoming PDRs. Last week's presentation of a PDR checklist for all of the subsystems was complemented by this week's systems meeting, during which the reliability team discussed their ongoing reliability prediction efforts in order to educate the team on subject matter that PDLs (Product Development Leads) will be presenting in the upcoming months. In addition to describing the results of previous analyses, the reliability team tasked the PDLs with data deliveries so that our reliability picture can be as complete as possible by the subsystem PDRs. In other news, circuit-level Peer Reviews have started, and are being supported by the systems team, subsystems, and independent chair people whom are determined by the responsible PDL and concurred by the Observatory Manager. A series of C&DH reviews are underway, with the DC/DC Converter Board and Downlink ASIC reviews recently completed and the PSE SDN, S Comm Card, Ka Comm Card, and Bulk Memory Card reviews scheduled for the next two weeks. The peer review process includes a long list of reviews that go thru December, leading to the Mission PDR in February. For the Instruments, e2v is 60% complete with the first run of the thin-gate batch for the 4k x 4k CCDs. A run of the e2v standard process thick gate batch is also in process and trails the thin-gate process by approximately two weeks. The thin-gate has more favorable radiation immunity and drive voltage characteristics and is the preferred process. However, to reduce risk, a separate run employing e2v's standard process was undertaken. We expect initially probe test results of the first batch in the late October early November time frame. The instrument ICD development process remains well underway. A final draft review and update of the 1553 requirements document was completed and should be ready for configuration baselining. We are coordinating an ICD review session with the EVE instrument team for mid-October (--AT-- GSFC). On the instrument contracts front, a no-cost extension to the HMI contract was completed. This gives us a little more room to complete the contract documentation work for the extension of the Phase A/Bridge contact to accommodate early Phase B work. We expect to complete the tech. eval. and pre-neg. plan this week and enter negotiations next week. Following this, we will finalize the technical evaluation and associated contract documentation for the remaining B,C, D, E phases of the HMI contract. Similarly, a letter contract has been executed for the EVE extension which allows us to complete the tech. eval. and associated pre-negotiation documentation for the EVE Phase B,C,D,E contract. We also completed the final internal reviews for the execution of the MIT Lincoln Labs Phase B contract for the EVE CCD detector. As usual, Carlos McKenzie & Kathy Tennant are doing an outstanding job with SDO contracts. The CM team: worked action items; updated the SDO document tree; prioritized intranet/database module work; & distributed 6 mechanical drawing files for review. Thanks, Ken "They conquer who believe they can." Virgil Roman Poet [ Attachment (text/x-html): 4721 bytes Character set: iso-8859-1 Encoded with "quoted-printable" ]