The weekly systems team meeting included a presentation on the updated bi-propellant system concept, including a detailed operations concept of the system configuration and operation through the various SDO operational phases. The Systems Team continues to work with the subsystems in preparing for the upcoming subsystem PDRs, including refining architecture concepts and reviewing subsystem level 3 requirements. As part of the concept development process, the C&DH and GN&C subsystems held peer reviews on various breadboard design implementation concepts, presenting emerging design details for review by the SDO subsystem and systems team. Finally, the systems team continues to work with the subsystem teams in supporting the ongoing LMSAL AIA accommodation effort. The subsystems have started to incorporating designs to accommodate AIA; all subsystem peer reviews planned in the next three months will reflect a design that accommodates the AIA. Mechanical Systems have determined that the optical bench design does not need to be changed for AIA. An assessment of the single event effects testing of the Atmel 1355 ASIC was completed by the Radiation group. Calculations of expected error rates based on the data indicate an upset rate of approximately 1 upset per 3 years per chip during solar minimum and 1 upset per 25 years per chip during solar maximum. Based on this assessment, the SDO Project is continuing to use the Atmel 1355 ASIC in non-critical to SDO survival applications. For the instruments, we worked the accelerated contract efforts for the Lockheed's AIA including generation of SOW and revision of JOFOC (Justification for Other than Full and Open Competition). In addition, we completed the technical evaluation of the Phase A extension proposal from HMI and continue to work on the final contract documentation for the Phase CDE contracts for EVE and HMI. This week the Ground System team successfully conducted their System Requirements Review. Approximately 32 RFAs were generated and accepted by the Project. Science Operational Working Group (SOWG) meetings are now being conducted weekly, a change from monthly. The MOC Design Engineer met with PAO to incorporate their input into the MOC design layout. The intent is to see if there is a design that would benefit VIP tours now that the HST MOC has been moved to Baltimore. The TSI vendor gave their front end (data) processor (FEP) demonstration on 10/02. Finally, the Ground System Manager successfully had the White Sands-GSFC MOU signed off by Codes 450, 460, 400, and Center Management. In the area of CM, the team: released 8 mechanical pull test drawings; worked action items & the CCR module of the database/intranet; & attended a Requirements Definition training course in order to better support the Project and to assist the Systems Engineering Team with requirements management and the writing of requirements. Thanks, Ken