The Subsystem and systems team participated in a variety of technical interchange meetings with the visiting EVE instrument team; focusing on mechanical, thermal, electrical, high-speed bus, 1553/software, and ground system interfaces. In addition, there were technical discussions on a few EVE potential design/configuration changes, such as the elimination of the OFS instrument (addressed later), an increase of the EVE high speed data bus allocation, and moving the EVE electronics unit back to the instrument module deck from its current location inside the spacecraft structure. In other areas, Document generation and review continues, with the emphasis on submitting each of the subsystem requirements documents into the CM system prior to each of the subsystem PDRs. The development teams met to discuss ACTEL SX72 and SX32 power sequencing issues and focus on developing a design implementation approach to address this problem. The Spacecraft design effort continues, with all subsystems making preparations for upcoming subsystem PDR Peer Reviews. The Project held their monthly budget and schedule reviews with all subsystems. Initial discussions were held on subsystem revised budgets that reflect a April 2008 launch. The SDO Project has requested that ACS, C&DH, EPS & Mechanisms subsystem teams ensure that a common vendor and common mechanical design is used for all Subsystem Data Node cards. This should allow programmatic benefits such as enabling common solutions to any problems found in one board design that are easily tracked and corrected in other common boards. The Ka Band subsystem team achieved excellent test results with their breadboard HGA feed horn. A high degree of correlation was found between simulated and tested radiation patterns and return loss. SDO team members attended the IFMP Town Meeting. For the Instruments, the first runs of the thin-gate and thick-gate processes for the e2v 4K x 4k CCD's were completed. The devices will be moved to the probe test station for the first electrical checks of the quality of the masking. Following these tests, we should have a better feel for potential yields and for acceptable device performance characteristics. We revised the AIA letter contract documentation based on the comments and suggestions received during the legal review. The final package was assembled and forwarded to legal for a final check. We should be able to release this contract shortly. Our attention now turns to completing the contract negotiations for EVE and HMI for the final Phase B, C, D, E contracts. The EVE technical team visited the SDO Project this week for ongoing discussions and update of the EVE to Spacecraft ICD's. The meetings were very productive and a solid requirements baseline has evolved. Updates will be incorporated and will provide a sufficient baseline of interface requirements for EVE's preparation for their upcoming instrument PDR. EVE has made a decision to delete the Optics Free Spectrometer (OFS) assembly from the EVE configuration. The OFS design was not maturing well enough to reduce the technical and programmatic risks identified during the SDO Systems Concept Review in April this year. EVE has determined an alternate approach (much lower risk) involving incorporation and use of additional calibration photo diodes to monitor short term calibration changes on-orbit and sounding rocket under flights for periodic checks of the absolute calibration change in the EVE instrument. HQ SEC has been briefed & we are in the process of assembling a presentation for HQ SEC so that they can understand & approve our OFS decision. These changes will slip the EVE PDR one into 12/03. The HMI team held two Engineering Peer Reviews in preparation for the HMI PDR. The HMI Optics Peer Review and HMI Filter Peer Review were conducted on Oct 22, 2003 with GSFC participation via teleconference (B. Thompson, D. Pesnell, and M. Scott). A detailed Instrument PDR agenda was received by the project for review and planning purposes. I would also like to welcome Mike Scott & Chad Salo to the SDO team. Mike is our GSFC Instrument Manager for HMI & Chad is our Instrument Accommodation Engineer. We are excited to have both of them on our team. In addition, Eric Grob (our AETD thermal lead) has accepted a detail to be our GSFC Instrument Manager for the new AIA Instrument and John VanBlarcom has taken over as the EVE Instrument Manager. We are finally staffed in the GSFC Instrument area & we are very happy with the team! The Ground System team updated their element-level schedules in support of their replan retreat next week where they will focus activities for the 4/08 launch. For CM, the team: continues to work fixes/enhancements to our intranet "Document Module" database; distributed draft versions of the Systems Engineering Management Plan (SEMP), Program Reliability Plan, & the Contamination Control Plan for review/comment; updated the document tree; & continued DOORS training. Thanks, Ken