The SDO development team is continuing the push towards both the subsystem-level and mission PDRs. The systems team completed an update of the Mission Requirements Document (MRD) and is planning on submitting the MRD into the CM document baseline process next week. The recent version of the MRD has been updated with recent configuration changes, including the incorporation of the AIA instrument. Generation and review of critical documents required by PDR (as defined by the SDO document tree) are continuing via the SDO CM system. Each of the subsystems is working to get their subsystem requirements and verification matrices into CM review prior to subsystem PDRs. These requirements will populate a DOORS database, easing the task of tracing requirements from one level to another. In other areas, the systems team has completed a re-evaluation of the mass and power budget and has released updated resource budgets along with margin (based on an assessment of subsystem maturity) to be carried and managed at the subsystem level, as well as still retaining margin at the system level for project reserves. The Subsystem Data Node (SDN) prototype is being used by the flight S/W team for developing diagnostic S/W, bootstrap/loader/monitor, and the board support package for the software bus. Work is also continuing in addressing SDN parts selection/implementation issues, backplane design, and the common Power Converter Card (PCC) design. Attitude Control Electronics (ACE) bread board development is progressing forward, folding in the comments from the recent ACE breadboard peer review process. The High Gain Antenna (HGA) commanding interface is being further developed, as well as an assessment of the HGA system jitter budget and its effect on the overall spacecraft jitter budget. The Observatory team continues to work schedule linkage/logic, critical path confirmation, control milestones for the subsystem leads, & phasing plans. The reliability team is working with the subsystems to develop FMEAs, Fault Tree Analyses, and Reliability Block Diagrams in preparation for the subsystem PDRs, the Systems Engineering PDR, and the Mission PDR. The SDO team held their first Launch Vehicle Technical Interchange Meeting with KSC this week. KSC provided a launch service program overview, along with facility capabilities and a launch vehicle procurement schedule. We also visited the Payload Processing Facility at Astrotech, as well as the Delta 4 and Atlas 5 launch provider facilities. The SDO/KSC team started work on the SDO Launch Vehicle Interface Requirements Document, which is required for the Launch Service Task Order process. A special thanks to Kevin Hughes (our L.V. I/F engineer) & the KSC team lead by Ron Mueller & Larry Craig for preparing & conducting a great meeting at KSC. After the push last week to finalize the AIA Phase A/B contract, focus turned to finalizing the arrangements for the upcoming HMI and EVE PDRs. We are working with the Code 300 System Review lead for SDO to refine the agenda and assemble the review panel for the instrument PDRs. We are inviting a couple of SDO Independent Review Team members to participate on the GSFC panels. We also worked with the HMI management team to coordinate the transfer of the e2v CCD contract from NRL to Stanford University. e2v is currently contracted by PRAXIS and we will maintain this relationship through the development phase to prevent disruption of the e2v CCD development efforts. PRAXIS has agreed to seamlessly transfer contract authority from NRL to Stanford for this work. AIA conducted its initial Science Team meeting this week. The SDO Project Scientist and AIA Instrument Manager attended. Finally, we coordinated the EVE presentation package for a presentation to Headquarters outlining the rationale for the recommendation to remove the Optics Free Spectrometer (OFS) assembly from the EVE configuration. The AIA team held its first science team meeting at Stanford University October 30-31. The meeting focused heavily on the science requirements of the AIA and the path to PDR. The Project Scientist met with the AIA science leads and began finalizing the full and minimum success science requirements. Several topical Science Working Groups are being established, to stimulate discussion and collaboration between the SDO science teams. Themes of the working groups include Space Weather and Geospace Connections. The first SDO Science Workshop is in the planning stages. The workshop will take place March 22-26, 2004 in Boulder, CO, and will be hosted by the EVE team at the University of Colorado. This workshop is open to all members of the international science community and will focus on the SDO investigation science goals and working group topics. A website will be up soon, with registration and travel information. A science organizing committee will establish the agenda for the meeting. The HMI team concluded its series of internal reviews with the Telescope and Focal Plane Assembly Peer Review this week. SDO subsystem members representing structures, thermal, and hardware QA participated in the review providing valuable insights. In addition, GSFC has provided feedback to the HMI team on the HMI Concept Study Report. Preparation has begun at both GSFC and Palo Alto for the HMI PDR on November 18 and 19, 2003. The EVE team and the SDO project are reviewing impacts to the relocation of the EVE electronics box to alongside the instrument. A slight FOV and glint issue is being looked at from the HMI telescope cover during deployment. EVE also met with MIT Lincoln Labs for technical CCD discussions - a peer review on the CCD is planned for mid-November. EVE PDR coordination is underway with a scheduled date of December 17-18 in Boulder, CO. A dry-run will be held November 12-13. The Mission Assurance team is nearly complete with the final round of document/negotiation reviews associated with HMI's Performance and Assurance Implementation Plan (PAIP) and Lockheed Martin's internal workmanship standards per the requirements set forth in the SDO Mission Assurance Requirements (MAR). The team also provided comments to the draft HMI Performance Verification Plan. Software QA participated in the recent Software Bus (SB), Remote Terminal (RT) and Health & Safety (HS) reviews and will document/track actions. The ground system performed a complete schedule, WBS, and budget overhaul this week at their three day retreat. A completely revised and more accurate representation of ground system development has been prepared and is ready for Project review. In the area of CM & Project Support, the team: now has the capability to add and edit user information in our intranet/database; distributed CCR for review (SDO-CCR-021: Solar Array Sizing); coordinated changes received from the review of the Single Board Computer Spec. and SOW; updated monthly CM calendar showing dates as to when documents were distributed for review and when comments are due; provided assistance to a few SDO team members on how to generate templates for documents; continued DOORS training; worked with the systems team to update the document tree & prioritize documents for the PDR; received approvals for Bldg 29 360 office mods; submitted SDO purchasing requirements into the SAP or Bankcard system; & completed preparations for the SDO AETD Champion Team meeting next week. In addition, we resolved an issue with the IFMP Help Desk concerning SDO's purchase request approval authority (known as Release Group Strategy) in SAP. SDO's Release Group Strategy was incorrectly moved by the IFMP Support Group in the SAP system and this, in turn, would send our purchase requests to the wrong organization for approval. We have been promised that this error will be corrected next week. Thanks, Ken