The SDO systems and subsystems teams continued the generation and review of SDO critical documentation in preparation for both subsystem and mission PDRs. The SDO Systems team submitted the Mission Requirements Document (MRD) for CCB review. The MRD, which is one of the primary repositories of the Mission Level 2 requirements, will be updated next week with any comments from the SDO team as part of this CCB document review and will be subsequently boarded by the CCB for baseline approval. Comments are due back from the SDO development team this week for the SDO Systems Engineering Management plan (SEMP), which is also planned to be submitted for CCB in the next week. The systems team supported the Deployables peer review, which provided the requirements and preliminary design details of both the solar array and high gain antenna (HGA) deployment systems. In addition, technical interchange meetings were held with various subsystem disciplines to address a variety of technical and developmental issues pertaining to SDO development and PDR preparations. These areas included parts and parts testing issues, instrument CCD temperature and recovery issues after SDO slew maneuvers, harness implementation issues, propulsion system thermal control, Omni antenna placement and resultant antenna coverage profile, and mechanical system design issues. The SDO team presented technical, schedule, and budget status at the AETD Champion Team meeting this week. All AETD subsystem leads presented, as well as the Observatory Manager, Systems Engineering, Instrument Systems and the Ground System. Budget negotiations began this week with subsystem leads over their revised budget to meet a April, 2008 launch. A meeting was held with the Rapid Spacecraft development Office to explore possible options for procuring spacecraft components. The SDO Project took delivery of the Single Board Computer Prototype this week. The Software team plans on installing and testing the vxWorks Operating System on this Prototype in the near future. For the Instruments, the team: worked the HMI Phase CDE tech eval; worked the final coordination details for the HMI PDR with the GSFC PDR chairman; reviewed the proposed Letter of Delegation for on site QA representation at Lockheed Martin for HMI and AIA; worked with the EVE team on the OFS descope justification presentation package for our upcoming meeting with Headquarters on the subject; and finalized the HMI SOW modification for the transfer of the Praxis contract from NRL to Stanford University for the e2v CCD development work. Exciting initial results were obtained during the first probe testing of the thin-gate and thick-gate batches for the 4k x 4k CCD's. To minimize risk the batches are split in half and tested separately. There are 20 CCD's per batch. A number of CCD's in each batch graded out as excellent which is a first indication that we will probably have good yield from these batches. Only a half-batch of each type have been tested thus far. Following the probe tests, DC parametric and initial image checks will be performed in ambient. So far so good. HMI is in the process of finalizing details and packages for the HMI PDR. A draft version of the presentation will be available electronically November 11th, with the final version available November 14th. A meeting with the code 300 review lead is scheduled to confirm the PDR agenda and discuss the review team makeup. The HMI team hosted Light Machinery for a Michelson interferometer PDR this week, and is in the process of reviewing the recent SDO CCRs involving the mass/power budget, and the updated mission requirements. For AIA, we held our first management telecon & we agreed on a management meeting at LMSAL on 11/20. LMSAL's AIA priority is to get SAO (Smithsonian Astrophysical Observatory, Cambridge, MA) under subcontract. SAO provides the telescope structure, optics, front door, and telescope assembly mounts for AIA. SAO also integrates LMSAL's secondary mirror/"spider" flexure assembly with mechanisms (focus mechanism for all telescopes; aperture selector mechanism for 1 telescope) and LMSAL's Guide Telescopes. SAO then optically aligns and tests the complete optical system prior to delivery to LMSAL for addition of the electronics and focal plane assemblies. We are in the process of working the AIA & Mission PDR options & schedule with GSFC/HQ mgmt. The EVE team finalized the plan for ESP and MEGS revisions as replacement for OFS calibrations and is ready to support a discussion with headquarters. Descoping the OFS is prudent due to the technology immaturity and the challenges OFS creates to the spacecraft in integration and restrictive magnetics. The descope will retire four RFA's from the SCR which identified challenges in the OFS portion of EVE. The EVE team is going forward with the dry-run PDR November 12-14 in preparation for the Instrument PDR on December 17 and 18. In the technical area, the EVE team is looking at conductive materials for the instrument purge lines in place of Teflon to prevent dielectric current strays per guidelines in the ICD. The Ground System team has been working/closing actions form their Systems Requirements Review. Key members of the team met with potential vendors and contractors to update them on the latest ground system requirements and discuss their ability to support the SDO mission. The second floor of building 14, in particular, the Attached Shuttle Payload Control area is being dismantled of all workstations, furniture, and other equipment in preparation for wall reconfiguration and renovation to support the SDO MOC. Finally, the MOC design engineer and several other SDO engineers are being featured in the Press and Sun Bulletin Newspaper in New York for a special article on Education. As part of the Education and Public Outreach initiative, SDO is joining the Chesapeake Children's Museum (CCM) in their December celebration of "A Century of Flight". SDO project personnel will be conducting activities that demonstrate the principles of flight dynamics, NASA's role in space flight, and a history of the Wright Brothers' early years at Kitty Hawk. Museum personnel will compliment the agenda with multi-disciplinary activities for children of all ages. In addition to the CCM collaboration, E/PO personnel are planning for another Dynamic Sun Workshop to be conducted in January. System programmers have initiated development of the Video Imaging and Photographic Requirements (VIPR) database. Approximately 200 images of ETU and prototype hardware currently reside on the SDO server. Beta testing for this system is scheduled for late December. In the area of CM, the team: released two mechanical drawings, handled miscellaneous requests regarding the database (password/username requests, info related to database, etc.) as well as questions regarding the document submittal process; distributed 2 CCRs for review and comment (SDO-CCR-030: Reallocation of Mass and Power Budgets and SDO-CCR-031: Baseline Release of SDO MRD); distributed tentative agenda for next week's CCB; continues to research the ITAR/export control rules which apply to SDO in order to guarantee we are compliant. Thanks, Ken "So much of what we call management consists in making it difficult for people to work." Louis (Satchmo) Armstrong (1900-71), American jazz trumpeter [ Attachment (text/x-html): ".prt4342754Jgb" 7759 bytes Character set: iso-8859-1 Encoded with "quoted-printable" ]