The spacecraft team continued to make progress towards preparing for a mission PDR early next year. The Ka Band and S Band PDR Peer Reviews were held this week. Budget negotiations continued with subsystem leads over their revised budget to meet a April, 2008 launch. The Software team started installing and testing the vxWorks Operating System on the Single Board Computer Prototype. The SDN team completed another significant milestone by making the pinout for the generic target available to subsystems for their breadboards. A byte swap issue in the SDN Prototype was also resolved by SDN team, allowing continued software development on the SDN Prototype. The first workshop for the entire SDO Science team, "Connecting our Dynamic Sun to the Heliosphere and Geospace" will be held on March 23-26, 2004 in Boulder Colorado. The website can be found at: http://lasp.colorado.edu/sdo/meetings/Workshop2004First.html HMI completed preparations for next week's HMI PDR & they have provided an electronic copy of the presentation package. In addition, the tech eval for the HMI CDE proposal was completed and the pre-negotiation plan is in work. EVE conducted a dry-run of their PDR presentation with SDO Project participation. Arrangements were made with Lockheed Martin to kickoff face-to-face technical discussions of the AIA mechanical/thermal accommodations with the spacecraft following completion of the HMI PDR. LMSAL selected Gary Kushner as the AIA Deputy Program Mgr, reporting to Larry Springer. Gary is transitioning from his duties as Solar-B FPP Systems Engineer. We continue to work PDR scheduling with our desire to have the Mission PDR early March 04 with the AIA Instrument PDR mid April 04. Pending IRT availability/work load & mgmt. availability for readiness reviews, this should enable us to maintain Confirmation before June 04. The Ground System article featuring SDO & our MOC design engineer can be seen at (3rd story down) http://www.pressconnects.com/monday/news/ Mission Assurance has completed their negotiations with Lockheed Martin on their Performance Assurance Implementation Plan (PAIP), internal workmanship standards, and a Letter of Delegation (LOD) for inspection support at Lockheed Martin for the HMI and AIA instruments. In addition, they met with the Attitude Control System (ACS) team to discuss and assess the level of mission assurance requirements that they will need for their contracts. Standard assurance requirement clauses appropriate to the class of components being procured are being developed for inclusion in the Statements of Work (SOW). The reliability team evaluated the degree of reliability improvement to the EVE Instrument by the addition of redundant elements within the EVE architecture. Even though some cost numbers still need to be finalized with EVE, the data seems to indicate that it is not cost effective to pursue additional EVE redundancy based on the minimal improvement to the overall science goals. For CM, the team: provided comments on EVE & HMI CM plans; distributed HMI PDR materials; prepared & conducted CCB for CCRs: SDO-CCR-021: Solar Array Sizing, SDO-CCR-024: SPN Split, SDO-CCR-030: Mass and Power Reallocation, SDO-CCR-031: Baselining of SDO MRD; completed & testing the intranet CCR module. I also welcome Mike Lilly (CSC - Planner) to the SDO team. Mike will be working with our Lead Planner, Jim Perry, in preparing/linking/tracking our numerous schedules. Thanks, Ken "The game of life is a lot like football. You have to tackle your problems, block your fears, and score your points when you get the opportunity." Lewis Grizzard GO RAVENS! [ Attachment (text/x-html): 4231 bytes Character set: iso-8859-1 Encoded with "quoted-printable" ]