The spacecraft team continued to progress this week towards Mission PDR. A CCB was held to put under configuration control the Systems Engineering Management Plan, Propulsion Subsystem Requirements, Mechanical Subsystem Specification, the Low Power Switch Card Requirements, the Power Converter Card Requirements, and the 1553 Bus ICD. The Propulsion Subsystem Development Plan and the Ka-Band Subsystem Development Plan were distributed for AETD Branch Head signature. The cPCI working group met to discuss issues with qualification of cPCI connectors, and possible solutions for SDO. A decision will be made next week pending discussions with vendors on which connectors to use for ETU and Flight. A meeting was held with the Rapid Spacecraft Development Office to explore SDO component procurements through an existing contract arrangement. For the Instruments, we conducted Risk Management coordination meetings with Lockheed Martin (HMI/AIA) and the University of Colorado LASP (EVE) management teams. Overviews of the SDO and instrument teams risk management processes were discussed and alignment of risk grading scales and reporting formats were worked out. The meetings were very useful and productive. A technical/programmatic meeting has be scheduled with e2v and RAL for Feb. 9 to review progress, schedules, flight contract proposals, and contract progress. The commissioning of the e2v test camera is nearing completion and CCD image test results should be available for this meeting. The processing of the second batches of the thin- and thick-gate devices is proceeding well and are nearly completed. e2v also expects to present probe test results of these batches during the Feb. 9 meeting. The design of the new epitaxial process ASIC has been completed and released to the foundry for manufacturing. Manufacturing and packaging of the SECCHI ASIC is in process as a backup approach to the new epitaxial ASIC. The new ASIC is preferred for improved radiation hardness and performance, however, RAL has some confidence the SECCHI ASIC's could be used as a backup. The plan is to package the SECCHI ASIC, build the supporting board and conduct on-the-bench tests to confirm whether it can indeed be used as a substitute device if necessary. An alternate approach using improved radiation hardened ACTEL FPGA devices is also being pursued. HMI released specifications for the HMI Electronics Box (HEB) bridgeboard, HEB motherboard, and filters along with drawings for the filter and beam splitter. HMI is sending responses to twenty-two of the HMI PDR RFAs on January 30, 2004. The HMI team is preparing for the Oven Structure, HEB Enclosure, and Optical Mount Alignment Method peer reviews to be held at LMSAL on February 4th. Materials will be distributed to the SDO Project on February 3. SDO personnel will participate via telecon. The AIA team made significant design progress on the filter-wheel, wavelength selector, and shutter mechanisms with internal reviews commencing in the next several weeks. Purchase orders were issued (SAO) for the Phase A multi-layer coating development work and procurement was started for the mirror blanks. SAO began the structural modeling analysis of the telescope mount design and started analysis of the 1-G release and thermal effects. In addition, the AIA team continues working on the Concept Study Report, which is due 2/15/04. For EVE, preparations continue for the third I/F working group meeting next week at LASP. The goal of the meeting is to have the ICD ready for baselining in February. A SDO and Instrument Grounding, Shielding and Bonding Technical interface meeting will follow on Thursday with members of the HMI and AIA teams joining us in Boulder. The ground system team successfully held its first of 5 peer reviews. The networks review went very well generating about six RFAs. Most RFAs suggested research into alternative network methods to reduce cost or to improve network robustness. Two other peer review packages are in final review, and the remaining two are in draft. The ground system manager coordinated a meeting with Center Management and key Project personnel to discuss the current policy on spacecraft encryption/security. At this time, no fully endorsed policy is in place. The project will proceed forward with spacecraft and ground system design with security vulnerabilities in mind, and to be aware that a GSFC security process/guidelines will be forthcoming. Finally, the first draft cycle and review of the MOMS and NENS contract task orders were performed this week. In the area of CM, we focused on documents (checking reviewers, notifying delinquent reviewers, and preparing for the CCBs) and started inputting the CCRs which have been processed into the database. Thanks, Ken "I don't know the key to success, but the key to failure is trying to please everybody." Bill Cosby [ Attachment (text/x-html): 5180 bytes Character set: iso-8859-1 Encoded with "quoted-printable" ]