The Systems team continued the review of SDO requirements documents in order to update and baseline them as part of preparation for the upcoming SDO PDR. The first PDR dry-run is scheduled for 2/19-20/04. The weekly systems team meeting addressed the topic of Spacecraft resets, with a detailed working discussion among all spacecraft electrical subsystems on their reset approaches and implementations, with the goal of working out lingering issues and coming up with a top-level agreement and description of how resets are implemented on the SDO Spacecraft. The Systems team also met to discuss the updated SDO jitter/pointing/alignment budget updates after the most recent round of meetings with the instrument teams, with the goal of updating and baselining these budgets as part of the PDR preparation process. In other areas, further cPCI backplane connector meetings were held among the team and with a potential vendor, followed by a project level meeting to evaluate potential options on how to proceed. On the hardware S/C hardware front, good progress is being made with development of the Ka Transmitter breadboards and LiIon battery testing is going well. Detailed interface and ICD baselining discussions were conducted with the EVE team this week. We also held a very productive grounding philosophies/practices TIM with all the Instrument teams. The HMI team completed their peer reviews this week with the beam-splitter mount, oven structure, and HMI Electronics Box enclosure. The Project received the first batch of responses to the HMI PDR RFAs, with all remaining responses expected by the end of February. The effort to provide a subset of common documents for AIA and HMI continued with the release of the AIA/HMI PAIP. Progress on the Lyot filter was made this week with the receipt of KDP crystal samples and calcite. An HMI vendor, Lambrecht, is now evaluating the quality of the calcite. In the area of EGSE, HMI commands were successfully sent from a sun workstation to the Start-Up ROM. AIA continues work on the concept study report and proposal. In support of the March 4, PDR-1, LMSAL has submitted a draft agenda for review and is refining the WBS and schedules with their prime subcontractor (SAO). SAO also delivered their proposal for the definitized Phase A sub-contract. LMSAL released/submitted the AIA EEE parts list and the Materials & Process list will be released by the end of this week. A parts control board has been set for February 24/25. LMSAL worked to refine the requirements for the telescope optics sizes, i.e.- shape of the optics, size of obscured and uncoated sections of the primary mirror, and elements of the optical prescription. Internal reviews were completed for the filterwheel design, Camera Electronics Box (CEB) & CCD camera radiator sizing, and CEB mounting configuration. An order for two life test filterwheels is now in place; the HMI/AIA mechanisms life test chamber has been cleaned and is currently under high vacuum; internal GSE has been designed and specified with several components on order. The ground system team successfully conducted their Operations Peer Review this week in which the Instrument teams supported/presented. The MOC Peer Review package was completed this week and the review will be held 2/11/04. In the area of scheduling, we published the schedules on our server for statusing in support of next week's Project monthlies with each subsystem lead. The team also refined control milestones and worked I&T iterations/flows. This week, the CM team: prepared for our CCB were we baselined several documents; inputted CCR files into the CCR intranet database; updated the WBS; & assisted in setting up a computer line in our conference room. Thanks, Ken "What may be done at any time will be done at no time." Scottish Proverb [ Attachment (text/x-html): 4107 bytes Character set: iso-8859-1 Encoded with "quoted-printable" ]