SDO Weekly Report for May 21, 2004 Last Friday, the SDO Project, together with the LWS Program and the IIRT, provided a pre-brief to Code S of the LWS/SDO EPMC presentation that is scheduled for May 26, 2004. The Mission Confirmation Briefing to the Agency PMC is still scheduled to place on June 2nd. SDN Breadboards continue to be built up; some boards are being completed with existing 512kB SRAM parts to work around the delay experienced in receiving 2 mB SRAM parts. The delay was caused by a software problem the vender (3D PLUS) was having. 3D PLUS reports the problem has been resolved and the current plan is to ship the SRAM parts on 6/15/04. Layout effort continued for the GCE GIC and GCE ASD, SPN PCC and LPSC, ACE RWI, and C&DH Ka Com, S Com ASD, BMC, Overlay and PSE ASD Breadboards. A task through the MSES contract was exercised for provision of the Gimbal Actuator and ECRA . The SSPA Breadboard #2 was in assembly. A number of ACS, Propulsion and Ka Band Specs and SOWS were completed and scheduled to be baselined via a SDO CCB meeting next week. The ACS subsystem and Spacecraft simulator requirements were baselined in the SDO project CCB meeting. Members of the AIA and HMI instrument teams from Lockheed Martin and Stanford attended an Interface Working Group (IFWG) meeting at GSFC with significant progress being made towards the projected baseline release of instrument ICDs. Systems implementation and design topics that were addressed included SDO High Speed Bus Design, Spacecraft time keeping/distribution, pointing and alignment requirements, Guide Telescope interfaces, mechanical interfaces, contamination and I&T. In parallel, the first monthly programmatic review of HMI and AIA was held. The PDR level AIA reduced thermal model was delivered to the SDO project. HMI has submitted responses to the Mission PDR RFAs. This week the ground system team visited the last vendor site of the three companies responding to the Antenna RFI. Six hours of detailed technical information was exchanged between SDO GS and vendor engineers. This purpose of these visits is to ensure proper RFP responses on the first release of the Antenna RFP in June. The audit of SDO's controlled property, conducted by the Property Management Branch and a member of the Project Support Team, was successfully completed with a 100% score. We would like to welcome our newest member of the Project Support Team, Donyea Burroughs. Donyea will be replacing Terry Hynson, as Terri is moving to the NPP Project next week. Regards, Rob Lilly SDO Deputy Project Manager (301) 286-7752 [ Attachment (text/x-html): 2825 bytes Character set: us-ascii ]