From Liz Citrin: SDO Weekly Report for August 20, 2004 The AETD Champion Review of SDO subsystem budget, schedule and status was held on Monday. The review, co-chaired by the Project and the SDO "Champion" Dennis Andrucyk, was attended by the LWS Program Manager and the SDO Program Executive. The Project feels that the Champion meetings provide a valuable forum for interaction with AETD technical management on SDO progress and issues. The Project risk meeting focused on the Ka-band transmitter, with a discussion of progress and risk mitigation plans by the subsystem lead and transmitter designer. As reported at MSR, Breadboard #3 of the Solid State Power Amplifier (SSPA) has achieved mission performance requirements. This retires a major design risk. However, potential SSPA performance degradation over mission life remains a risk. Preparations for an accelerated life test are in progress. TriQuint, the vendor of the Monolithic Microwave Integrated Circuit (MMIC) devices used in the SSPA, will perform the die attachment of the life test samples; additional samples will be evaluated for attachment results. Life test results should be available in early November. As backup, a Traveling Wave Tube Assembly (TWTA) approach will be pursued. The subsystem lead, Mike Powers, has received some responses to a TWTA RFI and will move forward on preparations of a Spec and SOW for a procurement. The Systems team will coordinate an evaluation of the impacts of a TWTA approach. A November decision is planned. A meeting was held between SDO Project Management, Quality Assurance and the Attitude Control Electronics (ACE) team to discuss the outcome of risk reduction efforts relating to board manufacturability of the ACE backplane. Discussions centered on solderability concerns related to the original ACE backplane design, which had up to 7 interconnects on plated through holes, causing difficulty in obtaining adequate solder fill and wetting. The consensus of the group was that the work shows that the number of interconnect to any one plated thru hole should be limited to 4 (& 4 oz. of copper) or less. This modification will greatly improve the solderability characteristics of the redesigned Printed Circuit Board. This interconnect limitation will be disseminated to all SDO designers. The weekly SDO systems meeting addressed the development and use of the SDO Flatsat, which uses ETU hardware to act as a test, verification and simulation testbed for the project. The meeting centered around Flatsat responsibilities, location, and use and was attended by the various disciplines on the team that make up the Flatsat contributors and users. Technical discussions were also held on in-house flight board design and manufacturing issues as part of preparing for ETU and flight designs, focusing on ensuring the proper mechanical/thermal analysis is conducted to guide flight board manufacturing approaches, investigation of current manufacturing approaches and potential process improvements, and specific parts mounting issues and strategies to accommodate ETU/Flight board design issues. Progress on the ACE box was good this week with receipt of the reaction wheel card and completion of ASD card testing. An RFI was released for a Digital Sun Sensor. The Gimbal Control Electronics (GCE) Subsystem Data Node (SDN) Core was successfully tested by Flight Software personnel and delivered to High Gain Antenna Subsystem personnel. A Kaparel chassis was received and is in process of being modified for integration and testing of the GCE SDN Core Breadboard and GCE Application Specific Design (ASD) Breadboard C&DH received 9 Overlay cards. 4 of cards had to be returned for rework due to drilled holes being out of tolerance. This rework has not affected subsystem progress, as there were enough boards for subsystems to continue work. The Propulsion subsystem reported having difficulty getting welds certified. SDO?s AETD Champion has offered assistance in persuading current contractor to provide more support, and is also seeking to identify another contractor that can assist the propulsion subsystem in this effort. LMSAL and SDO reached agreement on the AIA Phase C/D/E contract fee plan. LMSAL completed their subcontract preparations with SAO and a baseline schedule is being prepared for next week's quarterly project review. The SAO SOW and Telescope Assembly specification were released and the development effort continues with the fabrication of numerous Structural Model (SM) prototype components and ordering of surrogate mirrors for coating development. Development testing results for the 193A channel were evaluated and final fabrication parameters were selected. Testing of the mounting leg ball-joint successfully demonstrated reproducible pre-load with a Belleville washer design. A preliminary radiation ray trace analysis of the AIA optics package was completed. Gamma and proton radiation testing of the HMI/AIA mechanisms encoder boards is currently in process. Layout of the housekeeping board was completed and is being sent out for fabrication. The mechanism board for HMI has been assembled and the oven controller and oven pre-amp boards are currently in assembly. The executive peer review for the SUROM is complete with no major issues identified. The kernel development and STOL procedures for the SUROM testing is progressing for an acceptance test target date of August 26. The packaging analysis of the SECCHI waveform generator (WFG) ASIC used in the Camera Electronics Box has started. A test plan for has been finalized, and the first step in the plan has been completed. Expected results from the WFG ASIC analysis are due in early September. The HCM life test motors are being assembled and the life test is due to begin in mid-September. EVE is making good progress with the demonstration CCDs and supporting mechanical structure. Electronics development at LASP is lagging somewhat--the FPGAs found in the power services card and the Instrument controller electronics card are now considered the critical path items and the EVE Project Manager is focusing attention on the FPGA development lead by Neil White. Recent progress includes several electronics peer reviews held this month with participation by Steven Graham of code 500. The EVE team continues to work to define the instrument contamination requirements. The SDO Contamination Control Plan was baselined this week without all of EVE?s requirements. A CCR to the Plan will be necessary when the analyses are complete later this month. The ground system has performed week long testing on the new In-Snec Front End Processor (FEP). The unit is working very well so far. Also, the TSI FEP continues to work with no problems other than the original 'start-up' problems one month ago. A possible third FEP vendor has become known and the ground system team is investigating the possibility of receiving a demo on this unit. The Ground System Readiness team presented the 'road to CDR' at the ground system System Engineering meeting on Monday. This presentation went well. Proofs for all four Planet Walk Sun panels (on the B&A trail) have been approved. The panels are now in fabrication and will be delivered on time for the September 18th Grand Opening. A meeting was held to discuss the next planet on the agenda: PLUTO. Present were the SDO E/PO Goddard staff, representatives from the Planet Walk Committee, and E/PO staff from APL. APL has agreed to participate and will be providing text, images and graphics for the Pluto panels. -- Liz Citrin SDO Project Manager 301-286-1222 FAX 301-286-0214 Cell 410-241-0503